Data copyright © High Speed Two Ltd. unless otherwise stated
This work is licensed under a The Open Government Licence (OGL).
High Speed Two Ltd.
2 Snowhill
Queensway
Birmingham
B4 6GA
United Kingdom
Tel: 08081 434 434
This collection comprises site data from a Construction Integrated Recording at Northern Sustainable Placement Area Western Mound, Ruislip carried out by Archaeology Wales from May 2021 to May 2022. This includes the scanned paper archive (context sheets, registers, sample sheets, drawings), digital photos from the excavation stage of the evaluation, as well as spreadsheets and specialist reports created during the post-excavation phase of the project.
Skanska Costain Strabag Joint Venture (SCSJV) commissioned a programme of Construction Integrated Recording (CIR) on land at Newyears Green Lane, Ruislip, London Borough of Hillingdon to examine the site of, and an area surrounding, Bronze Age, Iron Age and Medieval features identified by evaluation trenching. The report in this collection outlines the work undertaken on site, the subsequent programme of post-fieldwork analysis, and the results of the archaeological Construction Integrated Recording.
Archaeological monitoring was undertaken over 62 days between the 12th March 2021 and 27th May 2022 and grouped into four phases of works. The work comprised the monitoring of ground clearance, topsoil stripping and excavations for foundations for an access road, a wheel wash, a haul road, laydown area, the area of the western mounds and the excavation of a pond. Archaeological features were observed during the works within Phases 3 and 4.
Phase 1 was conducted between 12th March and 30th April 2021. A total of 800m2 was stripped for the construction of an access road. The installation of a wheel wash required topsoil stripping of 315m2 and excavation of 160m2 for the wheel wash foundation. The removal of topsoil from c. 5400m2 for the construction of a haul road and laydown area.
Phase 2 of the works consisted of the excavation of an attenuation pond within the southwestern corner of the site. This was phase of work took place between 29th and 30th July.
Phase 3 took place between 1st and 7th September 2021 and consisted of the stripping of an area measuring 75m in length by a maximum width of 16m. This work was conducted to allow the construction of the haul road across this part of the site.
The final phase (Phase 4) of works took place between 11th April and 27th May 2022. Parcels 2-4 were stripped to allow the construction of the western mound.
The work was undertaken to contribute towards the following questions and GWSI-HERDS Specific Objectives:
The general aims of the archaeological evaluation were to:
Overall, the archaeological potential of the Northern Sustainable Placement is considered to be high with the features and material assemblage contributing to a number of the Knowledge Creation objectives (KCs) as outlined in the report.
The archaeology identified adds further detail to our existing knowledge of activity around New Years Green from the Palaeolithic period to the medieval period. As part of the next stage of post excavation analysis, all of the assemblages from the Northern Sustainable Placement Area should be analysed together so as to create a comprehensive picture of the archaeology of New Years Green.